Updates Diaphragm Wall Works
Earlier this year, we notified the community of our programme of piling and diaphragm wall activity as well as the concrete batching plant being constructed at the Old Oak Common Station Site. Until the plat is fully operational, at the end of July, we still require concrete to be delivered to site by concrete lorries.
Increased vehicle movements from Old Oak Common station site
From 1 to 31 July there will be an increase in concrete deliveries to enable the diaphragm wall activity. Lorries will travel from Victoria Road onto Old Oak Common Lane where they will access the site. These deliveries will assist with the safe completion of large concrete pours required for ground reinforcement works. Deliveries and concrete pours will take place during the extended working hours that were agreed with London Borough of Hammersmith and Fulham (LBHF) in January 2021.
This will be from 8am to 10pm Monday to Friday and 8am to 5pm on Saturdays. However, we will only work during the extended hours when necessary and we do not anticipate that the extra hours will be required on every weekday, or Saturday.
Further information can be viewed here