HS2 Works Notification: Update of works at Atlas Road roundabout in Victoria Road, April to May 2021

We previously notified you of the utility works for the Tunnel Boring Machine power supply. We are continuing with the programme of utility works in the Old Oak area, to provide power for the Tunnel Boring Machine to aid with the construction of the HS2 tunnels at the Victoria Crossover box (VCB) in Victoria Road.

Phase 1 of the works continue in Atlas Road which includes the laying of electrical power connections that will supply the power for the Tunnel Boring Machine and are scheduled to complete by 7th May.

For more information please see our works notification.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk .

Posted on 19th April 2021