HS2 Works Notification: Update: Next phases of utility works in Victoria Road, end of June to January 2022.

In February of this year, we wrote to you outlining our phased programme of works for the tunnel boring machine power supply along Victoria Road. The power supply works which started at Atlas Road roundabout junction with Victoria Road is now complete and the works moving south along Victoria Road, close to Tudor House will be completed by the end of June. On completion, our programme will continue along Victoria Road on the opposite side of the road, starting with the junction of Midland Terrace followed by the junction with Shaftesbury Gardens.

Schedule:

  • Victoria Road junction Midland Terrace, Late June– Late July 2021
  • Victoria Road junction with Shaftesbury Gardens, Early August – Early September 2021
  • Victoria Road in proximity to Midland Terrace to Chandos Road Junction, beginning September – Mid October 2021
  • For further information please see our update works notification.

    If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk .

    Posted on 25th June 2021