Update: Temporary extension of Old Oak Common Lane traffic management & surveys on Atlas Road. Ongoing site set up at Willesden Euroterminal and changes to manage Channel Gate Road

Temporary footpath closure and extension of lane closure north along Old Oak Common Lane and surveys on Atlas Road

From 5 October CSJV and Thames Water will be installing a water main from Old Oak Common Lane into the Old Oak Common HS2 station construction site. This will last for around four weeks. It will involve extending the existing lane closure up to the north of the site entrance.

On the 1 and 2 October CSJV will undertake pavement surveys in Atlas Road to monitor two drainage maintenance holes.

For more information about these works please read the notice here .

Update: Ongoing site set up at Victoria Road construction sites and at Willesden Euroterminal (WET) and changes to manage Channel Gate Road

SCS are finishing changing the hoarding boundary vegetation removal at Victoria Road sites tomorrow on Saturday 26 September .

SCS are continuing maintenance on the current rail infrastructure within the WET site which will be extended to Saturday working from 26 September to 31 October .

The postponed weekend work to install hoarding and gates at Channel Gate Road and Old Oak Lane will now take place on 3 and 4 October .

For more information about these works please read the notice here .

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email HS2enquiries@hs2.org.uk.

Posted on 25th September 2020